Renovating a house in White Rock: what needs a permit, and the 50% rule
White Rock needs a permit for moving interior walls, adding plumbing fixtures and finishing an unfinished space. Its Building Bylaw also has a rule that changes the cost of a large renovation: past 50% of the building's assessed value, the whole house must meet the Building Code.

In short, In White Rock, BC, a building permit is needed for renovating or repairing a building, removing, relocating, altering or building interior walls, finishing a previously unfinished area, installing new plumbing fixtures, and altering a fire suppression system, according to the City's February 2025 permit guide. Under Building Bylaw No. 1928, section 5.2, when renovation work exceeds 50% of the building's current assessed value, the whole building must be made to "substantially conform" to the Building Code, and an addition that increases floor area ratio by 25% requires sprinklers throughout.
White Rock's list of renovation work that needs a building permit is long. The City's Guide for Building Permit Applications lists moving interior walls, adding plumbing fixtures and finishing an unfinished space, and its Building Bylaw has a rule that can bring a whole older house up to the current Building Code. This post walks through both for a house in White Rock, from the City's February 2025 documents.
The renovation work that needs a permit
White Rock's guide says building permits are required for, but are not limited to, the items below. For a house renovation, these are the lines that apply:
- Repairing, renovating, or adding to an existing building.
- Removing, relocating, altering or constructing interior walls.
- Completing a previously unfinished area in an existing building.
- Altering a dwelling's fire suppression system when finishing a basement or creating a secondary suite.
- Installing new plumbing fixtures.
- Constructing chimneys, or installing wood stoves or inserts.
- Constructing, covering or enclosing a porch or sundeck.
- Constructing retaining walls over about 3.5 ft in height.
- Constructing a swimming pool, hot tub or spa pool.
- Demolishing, relocating or moving a building.
The words "not limited to" matter. The guide gives a minimum list, and it does not give a list of exempt work the way Abbotsford's bylaw does. A note on the guide also says no deposit of fill, excavation, alteration, repair, removal or demolition of any building or part of one may start without a permit. So in White Rock, we ask the City before treating any part of a renovation as exempt. Our post on renovation permits in Abbotsford shows how a city with an exemption list draws the line instead.
The 50% rule
The guide quotes Building Bylaw No. 1928, section 5.2: "When the value of proposed alterations, renovations, repairs, or an addition to an existing building exceeds 50% of the current assessed value of that building, the entire building must be made to substantially conform to the requirements of the Building Code and the Bylaws of the City of White Rock."
Two parts of that sentence decide whether it applies. The test uses the current assessed value of the building, which is the building portion of the property assessment and is separate from the land value. And it counts alterations, renovations, repairs and an addition together. Where the land carries most of a property's assessed value, the building's share is small, and a whole-house renovation reaches 50% of it with less work.
Once it applies, the scope is the entire building. Parts of the house that the owner did not plan to touch, such as the electrical service, the insulation or the guards on a stair, may need to come up to the current code as well. We check the assessment and price this rule before a design goes past the first sketches, because it can change a renovation into a project closer to a new house.
When sprinklers come in
The same section of the guide adds a sprinkler rule: when an addition increases the floor area ratio by 25%, the entire building must be fitted with fire suppression sprinklers. Floor area ratio is the house's floor area divided by the lot area. An addition that adds a quarter to the existing ratio therefore brings sprinklers into every room, including the rooms the addition does not touch.
Houses that already have sprinklers need care too. The guide lists altering a dwelling's fire suppression system, when finishing a basement or creating a secondary suite, as permitted work, and the interior renovation checklist asks for two sets of original sealed sprinkler drawings with hydraulic calculations, under the City's Fire Sprinkler System Bylaw No. 1683. Moving a wall in a sprinklered house can mean moving a sprinkler head, and the drawings show that the system still works.


What the renovation application needs
The interior renovation checklist for a single or two-family house or a houseplex lists the documents. They include the application form, Schedule 1 (the owner's acknowledgment of responsibility and undertakings), an agent authorization form, a land title search dated within 30 days, and two sets of architectural drawings. Two sets of sealed structural drawings are needed when the structural design does not meet Part 9 of the BC Building Code, the part that covers houses. Letters of assurance and insurance proof from each registered professional apply where professionals are involved, and the fee is paid when the application is accepted.
The drawings must show existing and proposed floor plans at a quarter-inch scale or its metric equal, with every partition and bearing wall, finished and unfinished areas, the room uses, the windows and doors, the stairs, the plumbing fixtures, appliances, hot water tank, fireplaces and heating, and the floor, ceiling and roof framing with beams and lintels. Cross-sections show ceiling heights and the floor, ceiling, roof and wall assemblies. Construction details show the effective insulation values, the continuity of the air and vapour membranes, and the fire and sound ratings of the wall assemblies.
The site questions on the checklist apply to renovations too. A property in the Geotechnical Assessment Area may need a landslide assessment report, and a property in the Flood Plain, Ravine and Significant Trees, or Watercourse Development Permit Area needs a development permit. Our post on building a custom home in White Rock explains each area.
- 01
List the work
Walls, plumbing fixtures, unfinished space, sprinklers, porch or deck: each is on the City's permit list.
- 02
Test the 50% rule
Compare the work's value with the building's current assessed value.
- 03
Check sprinklers
A 25% increase in floor area ratio means sprinklers throughout; altering a system needs sealed drawings.
- 04
Check the site
Geotechnical Assessment Area and the three development permit areas.
- 05
Book the appointment
Submit a complete package to a Building Official in person.
Source: City of White Rock, Guide for Building Permit Applications and Interior Renovation checklist (February 2025)
Basements and suites
Finishing a basement is permitted work in White Rock, because the guide lists completing a previously unfinished area. Adding a secondary suite at the same time brings in more of the City's requirements. White Rock's new house and additions checklist sets them out: the suite must be labelled on the plans, with its own heating controls and heating type, its own electrical panel placed outside the fire separation wall, passive air intakes in all bedrooms and one in the living room or kitchen, and a two-speed, continuous-running exhaust fan in the bathroom. The site plan must show a parking space of about 8 by 17 ft on the driveway for the suite.
The walls and ceiling between the suite and the main house need fire resistance and sound ratings, and the interior renovation checklist asks for those ratings to be shown on the wall assemblies. In a sprinklered house, the guide's line about altering the fire suppression system applies the moment the basement ceiling changes.
Outside work in the same job
Renovations often include work outside the house, and several of those items are on White Rock's permit list in their own right: constructing, covering or enclosing a porch or sundeck, building a retaining wall over about 3.5 ft tall, and building a pool, hot tub or spa. On a sloping White Rock lot, a new patio level can need a retaining wall, so we check its height early. Work that changes the outside of the house also needs a site plan with the setbacks, because the zoning bylaw applies to it.
Old materials and older houses
Before anything is opened in an older house, a hazardous materials survey shows which materials need special handling during demolition. Our post on the hazardous materials survey explains why it applies to every building and comes first. Check your home insurance before the work starts as well; our post on insurance during a renovation lists what to ask.
Electrical, gas and the appointment
White Rock's checklists list Technical Safety BC as the contact for natural gas and electrical permits and inspections, so those permits are separate from the City's building permit. A kitchen with a new gas range or a bathroom with a heated floor will need one.
The City accepts renovation applications by appointment only, booked at 604-541-2149, and does not accept incomplete applications. We prepare the full checklist before booking, as we do for a new house, because a missing document at the appointment means waiting for the next one.
The guide says a permit is issued once the plans are accepted as meeting the current BC Building Code and the City's bylaws, and the permit fees and bonds are paid. The fees are set in Schedule A of the City's Fees and Charges Bylaw No. 2447. A bond is money the City holds until the work is finished, so we include it in the owner's budget from the start.
Renovate or rebuild
In White Rock, the 50% rule and the sprinkler rule are why we price a large renovation and a rebuild side by side early. If the renovation crosses either line, much of the house is rebuilt to the current code anyway, and a new house may give more for the same scope. If it stays under both, a renovation keeps the existing structure and its lower scope. Our post on renovating or taking the old house down walks through that choice.
Frequently asked
Do I need a permit to move a wall in White Rock?
Yes. White Rock's Guide for Building Permit Applications lists removing, relocating, altering or constructing interior walls among the work that needs a building permit. The list starts with the words 'but are not limited to', so it is a minimum.
Does replacing a bathroom in White Rock need a permit?
Installing new plumbing fixtures is on White Rock's list of work that needs a building permit. Ask the City before treating a straight swap of an existing fixture as exempt, because the guide does not list an exemption for it.
What is White Rock's 50% renovation rule?
Section 5.2 of White Rock's Building Bylaw No. 1928, quoted in the City's permit guide, says that when the value of alterations, renovations, repairs or an addition exceeds 50% of the building's current assessed value, the entire building must be made to "substantially conform" to the Building Code and the City's bylaws.
When does a White Rock renovation need sprinklers?
White Rock's guide says an addition that increases the floor area ratio by 25% means the whole building must be fitted with fire suppression sprinklers. Altering an existing sprinkler system when finishing a basement or creating a suite also needs a permit, and the renovation checklist asks for sealed sprinkler drawings with hydraulic calculations.
Do I need an appointment to apply for a renovation permit in White Rock?
Yes. White Rock's renovation checklist says an appointment with a Building Official is required to submit a building permit application, and incomplete applications are not accepted. Appointments are booked at 604-541-2149.
Does a renovation in White Rock need structural drawings?
Only in some cases. The City's interior renovation checklist asks for two sets of sealed structural drawings when the structural design does not meet Part 9 of the BC Building Code, the part that covers houses and small buildings. Simpler framing can be shown on the architectural drawings.
We renovate and build homes in White Rock and South Surrey, and our White Rock page and renovations service show the work. To test a White Rock renovation against the 50% rule before you design it, book a free consultation. This post is general information based on the City's February 2025 documents. Check the City's current guide before you apply.
Sources
- City of White Rock, Guide for Building Permit Applications (February 2025)
- City of White Rock, Building Permit Application Checklist: Interior Renovation of a Single/Two-Family Dwelling or Houseplex (February 2025)
- City of White Rock, Building Permit Application Checklist: New Single-Family Dwelling, Houseplex, or Additions (February 2025)