Building a custom home in White Rock: the City's checklist, step by step
White Rock takes new house applications by appointment only, and asks for items a Surrey application does not: sealed sprinkler drawings, two sealed surveys, a landslide assessment on some lots and a view angle in two zones. Here is the City's checklist in the order we work through it.

In short, To build a new house in White Rock, BC, an owner books an appointment with a Building Official to submit a complete application, because the City does not accept incomplete ones. White Rock's February 2025 checklist asks for two original sealed topographic surveys, two sets of sealed sprinkler drawings under Fire Sprinkler System Bylaw No. 1683, a pre-construction BC Energy Step Code report, a geotechnical report for lots in the Geotechnical Assessment Area, and a 45 degree angle of containment check in the RS-2 and RS-3 zones.
White Rock asks more of a new house application than most cities around it. The City takes applications by appointment only, turns away an incomplete package at the counter, and asks for items a Surrey application does not, such as sealed sprinkler drawings and, on some lots, a landslide assessment. If you own a lot in White Rock or on the White Rock side of South Surrey, this post goes through the City's own checklist for a new house, dated February 2025, in the order we work through it.
Book the appointment last, and plan for it first
White Rock's Guide for Building Permit Applications explains the process. Planning and Development Services accepts applications, and an appointment with a Building Official is required to submit one. At the appointment the official does a first review to see whether the package holds every document needed for a detailed review. If anything essential is missing, the application cannot be accepted, and a second appointment is needed.
That changes how we prepare. In a city that takes emailed applications, a missing document starts an exchange with staff. In White Rock it ends the appointment. So we treat the City's checklist as a hard list, and we do not book the appointment until every line on it is ready. The number to book is 604-541-2149. We also bring the checklist itself to the appointment, ticked line by line, with each document labelled to match its line, so the official can find every item in the package.
Find out which special areas the lot is in
The first part of the new house checklist asks about the site. Each yes adds work before the building permit:
- Geotechnical Assessment Area: a geotechnical report prepared under the Engineers and Geoscientists BC guideline for landslide assessments for residential developments, with its Appendix D Landslide Assessment Assurance Statement.
- Flood Plain Development Permit Area: a development permit under the Official Community Plan.
- Ravine and Significant Trees Development Permit Area: a development permit.
- Watercourse Development Permit Area: a development permit.
Two associated permits also appear on the checklist: a Lot Servicing Application for the sewer, storm and water connections, and a Tree Management Permit Application. A development permit is a separate approval with its own review, so a lot in one of those three areas has a longer path than a lot outside them. Our post on when a project needs a geotechnical engineer explains what the engineer does, and our post on building on a sloped lot covers the design side of a hillside site.
Trees and the survey
White Rock's checklist asks for two original topographic surveys, sealed by a BC Land Surveyor. The survey must show the lot's dimensions and area, rights of way, easements and setbacks, existing and proposed buildings, ground levels to a datum, the driveway, the services at the street, and the elevations along any retaining wall at 10-foot spacing. It must also carry a statement from the surveyor that the elevations shown are natural grades, or the surveyor's estimate of natural grade before the site was altered.
The survey must show every tree on the property, on the City boulevard and next to the property, under the City's Tree Protection Bylaw, 2021, No. 2407. The checklist defines an off-site tree as a tree of any size within about 13 ft of the lot lines, including shared trees, and the tree survey records each tree's trunk diameter, drip line and the ground level at its base. The guide adds that a tree management permit is applied for at the same time as a demolition permit, and a demolition permit will not be issued before the tree permit is approved.


Height, grade and the view angle
On White Rock's slopes, height is measured from average natural grade. The checklist describes it as the average of the ground levels at the midpoints of the four walls of the building, and points to subsection 4.8 of the Zoning Bylaw. This is why the surveyor's statement about natural grade matters: the height limit is measured from it.
The RS-2 and RS-3 zones add a second limit. The elevations must show compliance with the angle of containment: a 45 degree angle drawn at about 19.5 ft above natural grade at the midpoint of the most southerly wall, or above the flood construction level. In plain terms, the south side of the house can rise to about 19.5 ft, and above that the building must step back under a 45 degree line. The south side is the side that faces the water, so the angle limits how much an upper floor can block the view from the lots behind it.
We draw the angle on the first massing sketch, before any floor plan. A design that ignores it has to be cut back at the upper floor after the plans are drawn.
The documents in the package
The checklist lists the documents an application must include. For a new house they are:
- The building permit application form, Schedule 1 (the owner's acknowledgment of responsibility and undertakings) and the owner's authorization form.
- A land title search dated within 30 days of the application.
- Two original sealed topographic surveys and two sets of architectural or design drawings.
- A pre-construction BC Energy Step Code compliance report, three pages only, with the reference house and the proposed house. The City asks applicants not to submit the energy model calculation sheets.
- Two sets of original sealed structural drawings.
- Two sets of original sealed sprinkler drawings with hydraulic calculations, under the City's Fire Sprinkler System Bylaw No. 1683.
- Two sets of sealed shoring and excavation plans, where the lot is in the Geotechnical Assessment Area or the foundation excavation is deep.
- Sealed letters of assurance (Schedule B for each registered professional, and Schedule A from the coordinating registered professional), proof of professional liability insurance and a certificate of insurance for each professional.
- The BC Housing New Homes Registration Form, where it applies, and the application fee.
The sprinkler drawings need planning early, and Surrey's new house checklist has no line for them. The sprinkler system needs a designer, hydraulic calculations and a water service sized to feed it, so it belongs in the design from the start.
- 01
Check the site
Geotechnical Assessment Area, flood plain, ravine and watercourse development permit areas, and the zone.
- 02
Survey and trees
Two sealed topographic surveys with natural grade and a tree survey under Bylaw No. 2407.
- 03
Design to the limits
Height from average natural grade; the 45 degree angle in RS-2 and RS-3; driveway slopes.
- 04
Engineer and sprinkler
Structural, energy, sprinkler and, where needed, geotechnical and shoring drawings, all sealed.
- 05
Appointment
Submit the complete package to a Building Official in person.
- 06
Permit and build
Permit after plan acceptance and payment of fees and bonds; electrical and gas through Technical Safety BC.
Source: City of White Rock, New Single-Family Dwelling checklist and Guide for Building Permit Applications (February 2025)
The drawings: driveway, envelope and suite
The checklist sets driveway rules on the civil plan. The crossing must be between about 15 and 19.5 ft wide. The driveway must slope up at least 2% from the road edge to the property line, so street water does not run onto the lot, and it may be no steeper than 15% from the property line to the garage slab. A back-sloping driveway, one that runs down toward the house, needs a linear trench drain connected to the storm system.
The cross-sections and details must show how the cladding meets sections 9.27 and 9.28 of the BC Building Code: wall-to-window and wall-to-door details, transitions between materials, intersections with roofs and decks, penetrations, flashing and the materials used. The air and vapour membranes must be shown as continuous, with their locations and materials.
If the house has a secondary suite, the site plan must show a parking space of about 8 by 17 ft on the driveway for the suite. The floor plans must label the suite and show its own heating controls, its own electrical panel placed outside the fire separation wall, passive air intakes in every bedroom and one in the living room or kitchen, and a two-speed continuous exhaust fan in the bathroom. The wall assemblies must give their fire resistance and sound transmission ratings.
Rebuild or renovate in White Rock
If you are weighing a large renovation instead of a new house, one rule in White Rock's guide changes the numbers. The guide quotes Building Bylaw No. 1928, section 5.2: "When the value of proposed alterations, renovations, repairs, or an addition to an existing building exceeds 50% of the current assessed value of that building, the entire building must be made to substantially conform to the requirements of the Building Code and the Bylaws of the City of White Rock." The guide also says an addition that increases the floor area ratio by 25% means the whole building must be fitted with sprinklers. On an older White Rock house, we price both rules before we compare a renovation with a rebuild.
Permit fees are set in Schedule A of the City's Fees and Charges Bylaw No. 2447, and the guide says the permit is issued after the plans are accepted and the fees and bonds are paid. Electrical and gas permits and inspections come from Technical Safety BC, which both City documents list as the contact.
Frequently asked
How do I apply for a building permit for a new house in White Rock?
By appointment. White Rock's guide says an appointment with a Building Official is required to submit a building permit application, booked by calling 604-541-2149. At the appointment the official checks that the package is complete, and an incomplete package is not accepted and needs a second appointment.
Does a new house in White Rock need sprinklers?
White Rock's new house checklist asks for two sets of original sealed sprinkler drawings with hydraulic calculations, and points to the City's Fire Sprinkler System Bylaw No. 1683 for details. The City's guide also says an addition that increases the floor area ratio by 25% means the whole building must be fitted with sprinklers.
What is the angle of containment in White Rock?
It is a height check in the RS-2 and RS-3 zones. The checklist asks the elevations to show that the house fits under a 45 degree angle drawn at about 19.5 ft above natural grade, measured at the midpoint of the most southerly wall, or above the flood construction level. It limits how high the south side of a house can rise.
When does a White Rock lot need a geotechnical report?
When the property is in the City's Geotechnical Assessment Area. The checklist asks for a report prepared under the Engineers and Geoscientists BC guideline for landslide assessments for residential developments, with its Appendix D Landslide Assessment Assurance Statement. Shoring and excavation plans are also needed in that area, or for a deep foundation excavation.
Which trees does the White Rock survey have to show?
All trees on the property, on the City boulevard and next to the property, under Tree Protection Bylaw, 2021, No. 2407. The checklist counts any tree of any size within about 13 ft of the lot lines, including shared trees, as an off-site tree, and the tree survey must be prepared by a BC Land Surveyor.
How steep can a driveway be in White Rock?
White Rock's checklist says the driveway must slope up at least 2% from the road edge to the property line, and be no steeper than 15% from the property line to the garage slab. The crossing must be between about 15 and 19.5 ft wide, and a back-sloping driveway needs a trench drain connected to the storm system.
Who issues electrical and gas permits for a new house in White Rock?
Technical Safety BC. White Rock's checklist and guide both list Technical Safety BC as the contact for natural gas and electrical permits and inspections.
For a lot on the Surrey side of the city line, our post on building a new house in Surrey covers that City's steps. We build custom homes in White Rock and South Surrey, and our White Rock page and custom homes service show how we work. To have the checklist above planned for your lot before the appointment is booked, book a free consultation. This post is general information based on the City's February 2025 documents. Check the City's current checklist before you apply.
Written by

Founder & President
Mark Van Ek is the founder and president of Venture Pacific, bringing 40+ years of construction experience in Metro Vancouver and the Fraser Valley, a 2026 HAVAN Award and several Georgie and HAVAN finalist placements to every custom home, renovation, and multiplex project.
Full profile