Septic and well for a new house in Langley: permits, setbacks and tests

How a septic system and a well are designed, filed, spaced and tested for a new house on a rural Langley lot, with the design flow worked out from the provincial manual and the distances that fix the site plan.

Mark Van EkNovember 15, 202610 min read

In short, A new house on septic and a private well in the Township of Langley needs two things before the building permit is issued: a Fraser Health record of filing from an authorized person (a Registered Onsite Wastewater Practitioner or a professional), and a well water potability certificate no older than six months. Under the Sewerage System Regulation (B.C. Reg. 326/2004), only an authorized person may build a Type 1 or Type 2 system, a Type 3 system or a flow over 9,100 L a day needs a professional, and a system must be 30 m from a domestic well (15 m for a holding tank) unless a hydrogeology professional advises otherwise in writing. The Sewerage System Standard Practice Manual (Version 3) sizes a house by bedrooms and living area: 1,600 L a day for 4 bedrooms up to 330 m², plus 3 L for each extra m². Its Table II-19 also sets 30 m from a dispersal field to a permanent stream or pond and 7.5 m to a downslope drain. Fraser Health charges $200 per filing, and the authorized person files a letter of certification within 30 days of finishing. Under the Groundwater Protection Regulation, a new well is sited 15 m from an existing water supply well, the casing stands at least 0.3 m above ground, and nothing may be stored within 3 m of the wellhead. Langley has flowing artesian wells in aquifers 58, 33 and 51, and the Brookswood, Hopington and Abbotsford-Sumas aquifers are among the most vulnerable in the Fraser Valley. The nitrate limit for drinking water is 45 mg/L (10 mg/L as nitrate-nitrogen).

A large part of the Township of Langley has no sewer and no Township water. Its community plan says rural areas are served by on-site sewer systems, and the Brookswood-Fernridge plan says most of that area runs on private systems too. So a new house on an acreage depends on two pieces of work that come before the building permit: a septic system designed and filed with Fraser Health, and a well with a recent water test.

Our page on acreage and farm homes in Langley lists the basic steps, and our page on building in rural Langley covers Glen Valley, the Salmon River Uplands and Milner.

Who is allowed to design and build a septic system?

The Sewerage System Regulation, made under BC's Public Health Act, sets this. A Type 1 or Type 2 system may be built or maintained only by an authorized person, or by an owner working on their own land under an authorized person's supervision. An authorized person is a Registered Onsite Wastewater Practitioner (ROWP), registered with the Applied Science Technologists and Technicians of BC, or a professional, such as an engineer with training in soil analysis and sewerage systems.

The regulation defines the types by how clean the water leaving the treatment is. Type 1 is treatment by a septic tank only. Type 2 produces effluent with less than 45 mg/L of suspended solids and a 5-day biochemical oxygen demand under 45 mg/L. Type 3 goes further: under 10 mg/L for both, and a median fecal coliform count below 400 per 100 mL. A Type 3 system, or any system designed for more than 9,100 L a day, must be supervised by a professional. Which type a lot needs depends on the soil the authorized person finds and the space left after the setbacks below.

A holding tank follows a different path. It stores sewage until a truck takes it away, and it needs a permit from a health officer, with a $400 fee, before it is built.

How a septic system is sized for a new house

The authorized person works from a daily design flow, the largest amount of sewage the system is expected to take in a day. The regulation points to the province's Sewerage System Standard Practice Manual (Version 3, in effect on its own since January 1, 2016) as the reference for standard practice. For a house, the manual sets the flow by the number of bedrooms and the living floor area. Each bedroom count has a maximum floor area, and each square metre above it adds 3 L a day. Each bedroom above six adds 300 L.

Minimum daily design flow for a house, by bedrooms and living area
2 bedrooms, up to 240 m²
1,000 L/day
3 bedrooms, up to 280 m²
1,300 L/day
4 bedrooms, up to 330 m²
1,600 L/day
5 bedrooms, up to 420 m²
1,900 L/day

Source: Province of BC, Sewerage System Standard Practice Manual, Version 3 (September 2014), Table II-8

Take a 4-bedroom house with 380 m² of living space. It is 50 m² over the 330 m² in the table, so its flow is 1,600 L plus 50 × 3 L, or 1,750 L a day. Add a one-bedroom garden suite of 80 m², which the table puts at 700 L, and the system is designed for 2,450 L a day. The manual adds the two flows together in its own example of a house with a carriage house. It also sets the average flow over any 30 days at no more than half the design flow, which is 1,225 L a day for this lot.

The manual says to use a per-person table for luxury homes, at 700 L a day for each person, so a large house can come out higher than the bedroom table suggests. A suite or second home decided late can mean a bigger field than the one already drawn, so we settle the number of bedrooms and any second home before the soil test is booked. On ALR land, the second home also has its own size limit, covered in building a house on ALR farmland in Langley.

What goes to Fraser Health, and when

Before construction, the authorized person files with the health authority, which is Fraser Health in Langley. Section 8 of the regulation lists what the filing holds: the owner's name and contact details, the type of building the system will serve, the type, depth and porosity of the soil at the site, plans and specifications with the authorized person's seal, and a written assurance that the plans follow standard practice. Fraser Health's bulletin for owners says a $200 non-refundable administration fee goes with it.

The filing has a time limit. Fraser Health says the system must be built within two years of the date it stamps on the Record of Sewerage System, and the regulation says that if no letter of certification is filed within two years, construction stops until new information is filed. In the Township, the record of filing must reach the permit office before the building permit is issued, so it is one of the first pieces of paperwork we start. Our Township of Langley building permit guide shows where it sits among the other documents.

Within 30 days of finishing the system, the authorized person gives the owner the plans, a maintenance plan and a copy of the letter of certification, and files the signed letter with Fraser Health, along with a plan of the system as built. From then on, the owner must maintain the system as the plan says and keep records of the maintenance. Using a system with no letter of certification on file is an offence under the regulation.

The distances that decide the site plan

Section 3.1 of the regulation keeps a sewerage system 30 m from a well that supplies a domestic water system, and a holding tank 15 m from one. A shorter distance is allowed only when a hydrogeology professional gives written advice before construction, and a copy of that advice goes to the health officer. The Standard Practice Manual adds more distances in its Table II-19, measured from the edge of the dispersal area (the field) and from any watertight tank.

Minimum distances from septic parts on a Langley lot

From the dispersal field

Domestic water supply well
30 m
High pumping rate well in an unconfined aquifer
90 m
Permanent stream, pond or lake
30 m
Seasonal stream
15 m
Downslope drain, such as a house perimeter drain
7.5 m
Drinking water line under pressure
3 m
Property line (guideline)
3 m

From a septic, treatment or pump tank

Domestic water supply well
30 m
High pumping rate well in an unconfined aquifer
30 m
Permanent stream, pond or lake
10 m
Seasonal stream
10 m
Downslope drain, such as a house perimeter drain
0 m
Drinking water line under pressure
3 m
Property line (guideline)
1 m

Source: Sewerage System Regulation, B.C. Reg. 326/2004, section 3.1; Province of BC, Sewerage System Standard Practice Manual, Version 3, Tables II-19 and III-16

The well circle takes the most room. On a lot of 4,050 m² (one acre), a well in the middle has a 30 m circle around it that covers 2,827 m², or 70% of the lot. That is why we place the well near one edge and the field near the other, with the house and driveway between them. The manual tells the authorized person to check these boundaries on the neighbouring lots as well, so a neighbour's well near the shared line can push the field further in. The Groundwater Protection Regulation works the same way in the other direction: a new water supply well must be at least 15 m from an existing one, unless the existing well is out of use, or one owner holds both and drills only one new well.

A farm adds more distances. The Township's Agricultural Construction Guide keeps buildings that house animals, and manure storage, 30 m from every well, a neighbour's well included. The manual also suggests 3 m between septic parts and driveways or other areas where the soil gets packed down, to lower the risk of the system freezing.

Country Shop, Langley, photo 12Country Shop, Langley, photo 17
Country Shop, a detached workshop we built on a rural property in Langley: the building from the garden side, and its gravel yard and lawn.See Country Shop

Drilling the well and looking after it

A registered well driller builds the well under the Groundwater Protection Regulation, and the well is registered in the province's GWELLS database. Some of the rules stay with the owner for as long as the well exists. The casing must stand at least 0.3 m above the ground around it. The ground must slope away so water does not pond at the wellhead. A well cap keeps out surface water, including flood water, along with debris, people and animals. And no one may leave or store anything within 3 m of the wellhead, or let material pile up there.

The owner also keeps the area around the wellhead clear of anything that would get in the way of repairs or inspection, including plants, and repairs the well when it needs it. The regulation sets 5 years as the time after which an unused well counts as out of service under the decommissioning rules of the Water Sustainability Act. Water for the house itself needs no licence, and the Township says domestic use includes watering a garden or lawn of up to 1,000 m².

Flowing wells in parts of Langley

In some parts of the Township, water can rise out of a new well on its own. The Township's advisory explains that a flowing artesian well taps an aquifer where the pressure pushes water above the ground without a pump, and that most of its flowing wells are in three aquifers: Nicomekl-Serpentine (Aquifer 58), West of Aldergrove (Aquifer 33) and South of Murrayville (Aquifer 51). The flow can start without warning during drilling.

Controlling that flow is required under sections 52 and 53 of the Water Sustainability Act and under the Groundwater Protection Regulation. A qualified driller or professional must stop or control it. If they cannot, the Township says it is the owner's job to hire another one, and to contact FrontCounter BC for a regional hydrogeologist if the flow still cannot be brought under control. On a lot in one of those three aquifers, we ask the driller how they will handle a flowing well before drilling starts.

What the water test should look for in Langley

For the building permit, the Township asks for a potability certificate with results no older than six months. That is one test on one day. HealthLinkBC advises a bacteria test at least once a year, and a chemical test when the well is finished and every year after. It names nitrate, fluoride and metals such as arsenic, lead, copper and manganese as the common chemicals of concern in BC groundwater, and says a safe result from a neighbour's well does not mean your own well is safe.

Nitrate deserves a close look in Langley. The drinking water limit is 45 mg/L of nitrate, which equals 10 mg/L measured as nitrate-nitrogen. HealthLinkBC says most BC groundwater holds less than 1 mg/L, that levels above 3 mg/L usually come from human activity, and that septic systems and farming are among the sources. It also says boiling does not remove nitrate, and that babies under six months are at particular risk.

  • The Township's 2009 Water Management Plan named three of the nine most vulnerable aquifers in the Fraser Valley as Langley aquifers: Brookswood, Hopington and Abbotsford-Sumas.
  • The Brookswood-Fernridge plan calls elevated nitrate in groundwater, from septic systems and farming, a major concern.
  • The Township's 2025 water report says Aldergrove groundwater has elevated iron, manganese and nitrate, and that one Aldergrove municipal well is above the 10 mg/L limit before it is blended with Metro Vancouver water.

So on a lot over one of those aquifers, we ask for nitrate and the common metals in the first test, while there is still time to plan treatment into the house. Township residents with a private well can join the Township's Private Well Network for free, which gives a 20% discount on water testing at one testing lab.

When Township water or sewer reaches the lot

Servicing can change after the house is built. The Township says that once a property connects to municipal water, the owner may have to decommission the well within 30 days of the connection, under Waterworks Regulation Bylaw No. 6074, and that a water main that does not run past the property is extended at the owner's cost. For a sewer connection, the Township's permit form says a septic owner disconnects the tank, has it pumped out and fills it with sand or clean fill. We note both on the site plan, so a future water line and a future sewer line have a clear route to the house.

The order we work in on a rural lot

Frequently asked

Can I install my own septic system on my Langley property?

Only under supervision. The Sewerage System Regulation lets an owner build or maintain a Type 1 or Type 2 system on their own land if an authorized person supervises the work. The authorized person, a Registered Onsite Wastewater Practitioner or a professional, still files the plans with Fraser Health and certifies the finished system.

How far does a septic field have to be from a well in BC?

At least 30 m from a well that supplies a domestic water system, and 15 m for a holding tank, under section 3.1 of the Sewerage System Regulation. A shorter distance is allowed only with written advice from a hydrogeology professional, given to the health officer before construction. The provincial manual asks for 60 m or 90 m to a high pumping rate well.

How big a septic system does a new house in Langley need?

The authorized person sizes it from a daily design flow. Table II-8 of the provincial Standard Practice Manual gives 1,300 L a day for a 3-bedroom house up to 280 m² of living area and 1,600 L for 4 bedrooms up to 330 m², plus 3 L a day for each extra square metre. A garden suite adds its own flow, for example 700 L for one bedroom up to 140 m².

What does Fraser Health charge to file a septic system?

Fraser Health's bulletin for property owners says a $200 non-refundable administration fee goes with the filing, and the system must be built within two years of the date Fraser Health stamps on the Record of Sewerage System. In the Township of Langley, the record of filing must be in before the building permit is issued.

What water test does the Township of Langley need for a new house on a well?

A well water potability certificate with test results no older than six months. HealthLinkBC also advises a bacteria test at least once a year, and a chemical test when the well is finished and every year after, with nitrate, fluoride and metals such as arsenic and manganese among the common concerns in BC.

Is nitrate a problem in Langley well water?

It can be. The Brookswood-Fernridge plan calls elevated nitrate from septic systems and farming a major concern, and the Township's 2025 water report says one Aldergrove municipal well is above the 10 mg/L nitrate-nitrogen limit before blending. HealthLinkBC says most BC groundwater has less than 1 mg/L, so a test is the only way to know.

What is a flowing artesian well, and where does Langley have them?

It is a well where the pressure in the aquifer pushes water above the ground without a pump. The Township says most of its flowing wells are in the Nicomekl-Serpentine (Aquifer 58), West of Aldergrove (Aquifer 33) and South of Murrayville (Aquifer 51) aquifers. The Water Sustainability Act requires the flow to be stopped or controlled.

Do I have to close my well when Township water reaches my Langley property?

The Township says that once you connect to municipal water, you may have to decommission your well within 30 days, under Waterworks Regulation Bylaw No. 6074. If the water main does not run past your property, it has to be extended at your cost.

We fix the bedroom count and any second home first, because they set the design flow. Then the authorized person tests the soil while the well driller looks at the well records for the area. The well goes in early, so the water can be tested and treatment planned before the house design is final. The field, the reserve area the manual suggests on some sites, the well, the driveway and the house are drawn on one plan, and the filing goes to Fraser Health in time for the building permit. If you own an acreage in Langley and want that plan made before you pay for full drawings, book a free consultation.

Written by

Portrait of Mark Van Ek, Founder and President of Venture Pacific
Mark Van Ek

Founder & President

Mark Van Ek is the founder and president of Venture Pacific, bringing 40+ years of construction experience in Metro Vancouver and the Fraser Valley, a 2026 HAVAN Award and several Georgie and HAVAN finalist placements to every custom home, renovation, and multiplex project.

Full profile