From first drawing to occupancy: the sequence a build actually follows

A build runs in a fixed order, and most of the time a project loses is lost by taking a step before the one it depends on. Feasibility answers what the lot and the existing house allow. Design turns that into drawings. The building permit converts drawings into permission. Construction follows a sequence of inspections that cannot be reordered. Occupancy comes when the authority having jurisdiction says it does. Understanding that sequence is what lets a homeowner tell a normal delay from a real problem.

Part of Building or renovating a home in Metro Vancouver. Figures re-verified 2026-09-06.

Key takeaways

  • Feasibility comes before design, because a design drawn against the wrong constraints has to be redrawn.
  • The building permit application is where an incomplete drawing set costs the most time.
  • Municipal review timelines differ across Metro Vancouver, so a neighbouring city's experience is a poor guide.
  • Construction follows an inspection sequence, and work covered before inspection may have to be opened again.
  • Renovation schedules carry more risk than new build schedules, because demolition can change the scope.
  • Occupancy is granted by the authority having jurisdiction, and it is the milestone that starts warranty coverage.

Feasibility, before anything is drawn

Feasibility establishes the constraints the design has to satisfy. On a new build it confirms zoning, lot dimensions, setbacks, height and floor area limits, servicing capacity, protected trees, and site conditions including slope and soil. On a renovation it adds the condition of the existing foundation and framing, and whether the intended scope crosses the threshold that pulls broader code compliance into the project.

This stage is short relative to the rest of the project and it determines whether the rest of the project is sound. A design produced before feasibility is a proposal about a house that may not be permitted on that lot, and redrawing it costs both the design fee and the calendar time.

The most expensive version of this mistake is commissioning a full drawing set before confirming that the site can be serviced. Where the answer comes back that the existing water or sanitary connection cannot support the proposed building, the drawings do not survive it.

Design, and the decisions that belong in it

Design turns the constraints into a building. It runs from concept through to the coordinated technical set that a permit application requires, and it pulls in consultants along the way: an architect or designer, a structural engineer, an energy advisor for the code compliance path, a geotechnical engineer where soil or slope requires one, an arborist where protected trees are present, and a surveyor.

Two decisions inside design have outsized effect on cost. The first is the building's shape and complexity, because corners, roof planes, and changes in level each add structure, envelope area, and labour. The second is the point at which selections are finalised. Selections locked before pricing produce a firm contract sum. Selections deferred become allowances, and allowances are the mechanism by which a fixed price contract stops being fixed.

This is also the stage where a builder involved early adds the most value, by pricing the design while it is still cheap to change. A design priced only after it is complete can require rework to reach the budget, and rework at that point costs design fees a second time.

The building permit

The building permit converts drawings into permission to build. In Vancouver, the City's building permit process covers new duplexes, single detached houses, and laneway houses, and the application requires a coordinated set of documents rather than architectural drawings alone: structural drawings, energy compliance documentation, and the supporting reports the site requires.

Where a development permit is also needed, it usually precedes or accompanies the building permit, and on a designated heritage property a Heritage Alteration Permit runs alongside as a second review track.

Review timelines are set by each municipality and differ across Metro Vancouver, which is why a neighbour's experience in another city is a poor predictor. Confirm the current timeline with the specific municipality for the specific application type at the point of applying.

The single largest controllable cause of permit delay is an incomplete application. A submission missing a required report or carrying uncoordinated drawings enters a correspondence cycle with the reviewer, and each cycle costs weeks. Time spent completing a submission before filing it returns more than it costs.

Construction and the inspection sequence

Construction follows a sequence dictated by the inspections the building department requires. The order varies by municipality, and the principle does not: certain work must be inspected before it is covered.

The broad sequence on a new home runs from excavation and footings, through foundation, framing, and the rough-in of plumbing, electrical, and mechanical, then insulation and airtightness, then interior finishing, then final inspections. Each inspection gates the work that buries it. Framing is inspected before insulation hides it. Rough-in is inspected before drywall closes the walls.

Work covered before its inspection may have to be opened again, and that is a cost and a schedule impact with no benefit attached. A well-run site treats the inspection calendar as part of the schedule rather than as an interruption to it.

On a renovation the same sequence applies to the new work, with demolition placed first. Demolition is where a renovation schedule is most exposed, because it is the point at which the actual conditions become visible and the scope can change.

StageWhat it producesWhat it gates
FeasibilityConfirmed constraints for the lot and structureWhether the design is worth drawing
DesignCoordinated drawings and consultant reportsWhether the permit can be applied for
Building permitPermission to buildWhether construction can start
ConstructionThe building, inspected in sequenceWhether work can be covered
OccupancyApproval to occupyWhen warranty coverage begins
Typical stage order, Metro Vancouver residential construction

Occupancy, and what it starts

Occupancy is granted by the authority having jurisdiction once the required inspections are satisfied. It is the point at which the home may lawfully be lived in, and on a new home it also matters for warranty: the 2-5-10 coverage periods run from occupancy or first transfer of title, whichever comes first.

A deficiency list is normal at this stage. The distinction worth holding is between deficiencies that prevent occupancy, which are typically life safety items, and those that do not, which are completed afterward under the contract. A builder who treats the deficiency list as part of the job rather than as an argument is the one worth engaging.

Venture Pacific carries projects through to occupancy and the deficiency list rather than treating the final inspection as the end of the work. On the Build side that closing stage is where a homeowner forms most of their opinion of the whole project.

Frequently asked questions

What is the correct order of steps for building a custom home in Metro Vancouver?

A Metro Vancouver custom home follows five stages in order: feasibility, which confirms zoning, servicing, and site conditions; design, which produces coordinated drawings and consultant reports; the building permit, which converts those drawings into permission; construction, which proceeds through a required inspection sequence; and occupancy, granted by the authority having jurisdiction. Taking a step before the one it depends on is the most common cause of avoidable delay and duplicated cost.

Why does a building permit application get delayed?

The largest controllable cause of building permit delay is an incomplete or uncoordinated application. A submission missing a required consultant report, or carrying drawings that disagree with one another, enters a correspondence cycle with the reviewer, and each cycle costs weeks. Review timelines are also set by each municipality and differ across Metro Vancouver, so confirm the current timeline with the specific city for the specific application type rather than relying on another city's experience.

Do I need a development permit as well as a building permit?

Whether a development permit is required alongside a building permit depends on the municipality, the zone, and the type of work. Where one is required it generally precedes or accompanies the building permit application. On a designated heritage property, a Heritage Alteration Permit runs as an additional review track. Confirm which permits a specific address and scope require with the municipality before assuming the building permit is the only approval needed.

What consultants do I need for a custom home build?

A Metro Vancouver custom home typically requires an architect or designer, a structural engineer, an energy advisor for building code compliance documentation, and a land surveyor. A geotechnical engineer is added where soil conditions or slope require one, and an arborist where protected trees are present on or near the site. On a heritage property, a heritage consultant joins the team. Which of these a project needs is established during feasibility.

Why does work need to be inspected before it is covered up?

Building inspections verify that structural, plumbing, electrical, and mechanical work meets code while it remains visible. Framing is inspected before insulation conceals it, and rough-in services are inspected before drywall closes the walls. Work covered before its required inspection may have to be opened again, which costs money and schedule with no benefit. A well-run site treats the inspection calendar as part of the construction schedule.

How much does design cost as a share of a project?

Venture Pacific does not publish design cost as a percentage, because the consultant team a project needs varies with the site and the scope. What determines it is which consultants the project requires, which feasibility establishes: a flat serviced lot with no protected trees needs a smaller team than a sloped lot requiring geotechnical work and an arborist report. Design and consultant fees are quoted against the specific project's requirements once those are known.

When should I involve a builder in the process?

Involving a builder before the design is finalised is where the most value is added, because the design can be priced while changes are still inexpensive to make. A design priced only after completion may need rework to meet the budget, and that rework incurs design fees a second time. Early builder involvement also brings buildability and site logistics into decisions that are difficult to reverse once drawings are complete.

What is a deficiency list and when does it get resolved?

A deficiency list records items requiring completion or correction at the end of construction, and it is a normal part of finishing a project. Deficiencies that affect life safety must be resolved before occupancy is granted. Others are completed after occupancy under the terms of the construction contract. The contract should state how deficiencies are documented, who verifies completion, and how any holdback relates to their resolution.

Why is a renovation schedule less predictable than a new build schedule?

A renovation schedule carries more risk because demolition can change the scope. A new build on a cleared site follows a predictable sequence against known conditions. In a renovation, the actual condition of framing, wiring, and subfloor becomes visible only once surfaces are opened, and what is found can require engineering, redesign, or a permit revision before work continues. Schedules for renovation work should carry that risk explicitly rather than assume nothing unexpected appears.

When does my home warranty coverage start?

Home warranty coverage on a new British Columbia home starts at occupancy or the first transfer of title, whichever comes first. That date sets the expiry of each of the three coverage periods under 2-5-10, so it determines how long materials and labour, building envelope, and structural coverage each remain in force. Confirm the recorded start date with the warranty provider rather than assuming it matches the move-in date.

Go deeper in the Journal

Sources and references

Rate and regulation figures on this page were re-verified on 2026-09-06. Construction cost ranges come from Venture Pacific's own Metro Vancouver projects and are described as such wherever they appear.

  1. Building permit, new duplex, single detached house, or laneway houseCity of Vancouver. Accessed 6 September 2026.
  2. BC Building Code 2024Province of British Columbia. In effect 8 March 2024. Accessed 6 September 2026.
  3. BC Energy and Zero Carbon Step Code requirementsProvince of British Columbia. Accessed 6 September 2026.
  4. Home Warranty Insurance: what homeowners need to know (2-5-10 coverage)BC Housing, Licensing and Consumer Services. Accessed 6 September 2026.

Let's talk about your property

A conversation, not a commitment.

Whether you're curious about the multiplex value of your land or looking to partner on a missing-middle build, we're here to start the conversation.