Walls, windows and air: insulation, thermal bridging, airtightness and heat recovery ventilation in BC homes

The shell of a house is its walls, roof, floors, windows and doors: everything that separates heated rooms from outside air and the ground. In an energy-efficient home the shell sets the heating demand that the Step Code limits. It holds heat in with insulation, keeps heat from escaping through the wood framing, uses windows that lose less heat, and stops air from leaking through gaps. Because a well-sealed house needs fresh air brought in on purpose, the BC Building Code requires a mechanical ventilation system, and a heat recovery ventilator is one way to warm incoming air with outgoing air. This chapter sets out the code numbers for homes in Burnaby, Surrey and the rest of Metro Vancouver.

Part of Energy-efficient homes in BC: the Step Code, testing, and heating. Figures re-verified 2026-10-24.

Key takeaways

  • Article 9.36.2.4 requires insulation values to account for the heat lost through studs, joists, lintels, sills and plates.
  • For buildings with only homes in places under 3,000 degree-days, Table 9.36.2.6.-C lists walls at RSI 3.08 and attic ceilings at RSI 8.67.
  • Table 9.36.2.7.-D lists a maximum window U-value of 1.22 for buildings with only homes, in every climate zone.
  • Article 9.36.2.9 requires a continuous air barrier across joints, between materials and around every penetration.
  • Every home with electrical power needs a mechanical ventilation system under Article 9.32.3.1.
  • A heat recovery ventilator must recover at least 60 percent of sensible heat at 0°C under Article 9.36.3.9.

How the code measures insulation

The BC Building Code describes insulation in two numbers. RSI is the metric measure of how well an assembly resists heat flow, in square metre kelvins per watt; a higher RSI holds heat better. The U-value, used for windows and doors, is the rate at which heat passes through, in watts per square metre per kelvin; a lower U-value is better.

The code asks for effective values, meaning the whole wall as built. Sentence 9.36.2.4.(1) says the calculation must account for the heat loss through closely spaced framing such as studs and joists, and through lintels, sills and plates. The code treats each stud as a thermal bridge: a path where heat escapes faster than through the insulation beside it.

Under the Step Code, an energy advisor can trade one part of the shell against another as long as the whole building meets its heating demand target. The code's prescriptive tables still show what a baseline home looks like, and the energy model compares the design with a reference house built to the base rules. The table below lists the values in Tables 9.36.2.6.-C and 9.36.2.7.-D, which Sentence 9.36.1.3.(6) applies to houses and to buildings that hold only homes.

These tables apply where a heat recovery ventilator or a heat pump is installed, under Sentence 9.36.2.6.(1). For buildings without either, Tables 9.36.2.6.-A and -B list walls at RSI 2.78 in places under 3,000 degree-days.

Part of the shellUnder 3,000 degree-days (Metro Vancouver)3,000 to 3,999 degree-days (for example Vernon)
Ceilings below atticsRSI 8.67RSI 8.67
Cathedral ceilings and roof decksRSI 4.67RSI 4.67
Flat roofs not used by peopleRSI 5.28RSI 5.28
WallsRSI 3.08RSI 3.69
Floors over unheated spacesRSI 4.67RSI 4.67
Windows (maximum U-value)1.22 W/(m²·K)1.22 W/(m²·K)
Minimum effective insulation and maximum window U-values for buildings containing only dwelling units (BC Building Code 2024, Tables 9.36.2.6.-C and 9.36.2.7.-D)

Thermal bridges and where insulation must stay continuous

A shell loses the most heat where insulation stops. Article 9.36.2.5 sets rules for those places. Where an interior wall, foundation wall, firewall, party wall or structural element passes through an outside wall or insulated roof, Sentence (2) says it must be insulated in one of three ways: on both sides for a distance of 4 times its uninsulated thickness, within the plane of the insulation to at least 60 percent of the required value, or within itself to the full value.

This matters for multiplexes. The party wall between two side-by-side homes meets the outside wall at every floor. That junction has to be detailed so the insulation runs past it. Sentence 9.36.2.5.(9) adds that joints between walls and other parts of the shell must be insulated to at least the lower of the two values that meet there.

Large structural parts that pass through the shell, such as balcony slabs, beams and columns, can be left out of the wall calculation under Sentence 9.36.2.4.(3), but only if insulation is fitted tight around them and their total area is no more than 2 percent of the gross wall area. A design with many balconies or exposed beams has to count them.

Pipes, ducts and wires inside walls are covered too. Sentence 9.36.2.5.(7) allows a reduced value at plumbing and electrical boxes and pipes, at least 60 percent of the required value, if the insulation behind them on the cold side is continuous. Sentence 9.36.2.5.(8) requires at least RSI 2.78 where ducts, pipes or cables run inside an insulated floor or ceiling.

The air barrier

An air barrier is the layer of materials that stops air from moving through the shell. It can be a sheet membrane, taped sheathing, sealed drywall or a mix, as long as the pieces join into one continuous layer. Article 9.36.2.9 requires a continuous air barrier system and says it must stay continuous across construction, control and expansion joints, across junctions between materials and assemblies, and around penetrations through every assembly.

That list explains where houses fail their air tests. A wall can be airtight across its middle and leak at the rim joist, where floor framing meets the wall, or around every pipe, vent and wire that passes through. Sentence 9.36.2.9.(3) also requires windows, doors and skylights to meet the air leakage limits in the North American fenestration standard and its Canadian supplement.

The step sets how good the result must be. Step 3 allows 2.5 air changes per hour at 50 pascals, Step 4 allows 1.5 and Step 5 allows 1.0, under Table 9.36.7.4. Going from Step 3 to Step 5 cuts the allowed leakage by 60 percent. Name one person on site as responsible for the air barrier, because every trade that drills through the shell can break it.

Fresh air: ventilation and heat recovery

A tight house needs a planned supply of fresh air. Article 9.32.3.1 requires every home with electrical power to have a mechanical ventilation system that meets CAN/CSA-F326-M or Subsection 9.32.3. The system must include a principal ventilation fan system that supplies air and has an exhaust fan, plus kitchen and bathroom exhaust fans, under Article 9.32.3.3.

Article 9.32.3.4 lists ways to supply that air. One is a ducted forced-air heating system with an outdoor air inlet and a fan that runs all the time. Another adds a heat recovery ventilator to that system. A third uses a heat recovery ventilator with its own ducts to each bedroom and each floor without a bedroom. A heat recovery ventilator, often shortened to HRV, passes outgoing stale air and incoming fresh air past each other so the fresh air picks up heat without the two streams mixing.

Sentence 9.32.3.4.(6) allows passive vents for supply air only in limited cases: a one-storey home under 168 square metres, with no ducted forced-air heating, in a mild climate, and not in a building that complies through the Step Code. Since new houses comply through the Step Code, this exception does not reach them, apart from a secondary suite.

Where an HRV is installed, Sentence 9.36.3.9.(3) sets its efficiency. In places where the January design temperature is -10°C or warmer, it must recover at least 60 percent of sensible heat at an outdoor test temperature of 0°C. Table C-2 lists the Metro Vancouver locations between -6°C (Ladner) and -9°C (Haney), so the 60 percent rule applies across the region.

Frequently asked questions

What is effective thermal resistance in the BC Building Code?

It is the insulating value of a whole assembly as built, including the heat that escapes through framing. Sentence 9.36.2.4.(1) requires the calculation to account for studs, joists, lintels, sills and plates. It is stated as RSI, and a higher number holds heat better.

What is a thermal bridge in a wood-frame wall?

It is a path where heat escapes faster than through the insulation around it. In a wood-frame wall, each stud, plate and header is a thermal bridge, because wood conducts heat faster than insulation. The BC Building Code counts these paths in the wall's effective value, and Article 9.36.2.5 limits gaps where other elements cut through the insulation.

How much wall insulation does the BC code list for homes in Metro Vancouver?

Table 9.36.2.6.-C lists an effective value of RSI 3.08 for walls in buildings that hold only homes, in places under 3,000 degree-days. That covers Vancouver, Burnaby, Surrey, Richmond and New Westminster under Table C-2. Under the Step Code, the energy model can trade wall value against other parts if the whole building meets its target.

What window U-value does the BC code list for new homes?

Table 9.36.2.7.-D lists a maximum U-value of 1.22 W/(m²·K) for windows in buildings that hold only homes, in every climate zone. Doors and skylights have their own limits in Tables 9.36.2.7.-A and -B. A lower U-value means the window loses less heat.

What is an air barrier in a house?

It is the continuous layer of materials that stops air from passing through the walls, roof and floors. Article 9.36.2.9 of the BC Building Code requires it to stay continuous across joints, between different materials and around every penetration. Its quality shows up in the blower door test.

Does the BC Building Code require a heat recovery ventilator?

No single device is required. Article 9.32.3.1 requires a mechanical ventilation system in every home with electrical power, and Article 9.32.3.4 lists several ways to supply air, some with an HRV and some without. Where an HRV is installed, the code sets its minimum efficiency.

How efficient must a heat recovery ventilator be in BC?

At least 60 percent sensible heat recovery at an outdoor test temperature of 0°C, in places with a January design temperature of -10°C or warmer, under Sentence 9.36.3.9.(3). Colder places also need at least 55 percent at -25°C. Metro Vancouver locations in Table C-2 fall in the first group.

How is a multiplex party wall insulated where it meets the outside wall?

Sentence 9.36.2.5.(2) gives three options: insulate both sides for a distance of 4 times the party wall's uninsulated thickness, insulate within the plane of the wall insulation to at least 60 percent of the required value, or insulate within the party wall itself to the full value. The junction is checked in the energy model and in the air test.

Can a new house use passive vents instead of a ventilation fan system?

Only in narrow cases, and new houses on the Step Code are outside them. Sentence 9.32.3.4.(6) allows passive supply vents for a one-storey home under 168 square metres, without ducted forced-air heating, in a mild climate, and not in a building that complies through Subsection 9.36.6. A secondary suite is the exception named in the rule.

Why does airtightness matter more at Step 5 than at Step 3?

Because the allowed leakage drops from 2.5 to 1.0 air changes per hour at 50 pascals, a 60 percent cut, under Table 9.36.7.4. Leaked air carries heat out, and Article 9.36.6.2 counts air leakage as one input to the heating demand figure that Step 5 caps at 15 kWh per square metre per year in Metro Vancouver.

What does an RSI value on an architect's drawing mean?

RSI is the metric measure of thermal resistance, in square metre kelvins per watt. It shows how well a wall, roof or floor resists heat flow, and a higher number is better. The BC Building Code states its insulation requirements as effective RSI values, which include the effect of framing.

Go deeper in the Journal

Sources and references

Rate and regulation figures on this page were re-verified on 2026-10-24. Construction cost ranges come from Venture Pacific's own Metro Vancouver projects and are described as such wherever they appear.

  1. British Columbia Building Code 2024, Book I (General), Revision 2: Division B, Sections 9.32, 9.33, 9.36 and 9.37, and Appendix C, Table C-2Province of British Columbia. Code in effect 8 March 2024. Accessed 24 October 2026.
  2. BC Energy Step CodeProvince of British Columbia. Page last updated 9 June 2025. Accessed 24 October 2026.