When zoning says no: rezoning, variance permits and the board of variance
When a lot's zone does not allow a project, BC law gives three routes, and each one can change different things. Council can rezone the lot, which can change use and density, sometimes after a public hearing. Council, or a staff member it delegates for minor cases, can issue a development variance permit, which can relax rules such as setbacks and height and cannot change use or density. A board of variance can allow a minor variance to siting, size or dimensions where a rule causes undue hardship, and its decision is final. An application on the wrong route cannot grant what the project needs.
Part of Multiplex zoning rules in Metro Vancouver. Figures re-verified 2026-10-23.
Key takeaways
- Rezoning is the only one of the three routes that can change the use or density allowed on a lot, and council decides by bylaw.
- A development variance permit under section 498 must not vary use or density, residential rental tenure or a flood plain specification.
- Council may delegate minor variances on siting, size, dimensions and parking to a staff member under section 498.1.
- A board of variance can allow a minor variance where compliance would cause undue hardship, and section 542 (4) makes its decision final.
- The board of variance must not make an order that conflicts with a section 219 covenant or applies to listed heritage property.
- Section 464 bars public hearings on rezonings that match the official community plan and are mainly residential.
Rezoning: the route that can change use and density
Section 479 of the Local Government Act gives a local government power, by bylaw, to divide land into zones and regulate within each zone the use of land, the density of that use, and the siting, size and dimensions of buildings. It can also set minimum and maximum sizes for new lots. A rezoning is an amendment to that bylaw for a specific lot or area, and council decides it.
Rezoning is the route for a change in the number of homes. Section 481.3 frames the small-scale unit minimums as a use and density of use, and the other two routes are barred from varying use or density. A project that needs more homes than the zone allows, or a building type the zone does not list, goes to rezoning. Richmond's bulletin gives one common case: development on more than one lot would typically need a rezoning to a townhouse or apartment zone.
Public hearings follow section 464. The default in subsection (1) is that a zoning bylaw needs a public hearing. Subsection (2) removes the requirement where an official community plan is in effect and the bylaw is consistent with it. Subsection (3) goes further: a city must not hold a hearing where the bylaw is consistent with the plan, its sole purpose is a development that is at least partly residential, and the residential part is at least half of the gross floor area. Subsection (4) bars hearings on bylaws passed only to meet the small-scale housing law. Burnaby and Port Moody both explained these changes to residents in 2024.
Inside a transit-oriented area, rezoning stays the route, with one change set by the province. Its FAQ says a city cannot deny a project on the ground that its density is too high, if the density is within the provincial limits for that tier. Our Journal post comparing rezoning with building under existing zoning covers the timing side of this choice.
Development variance permits: relaxing the numbers
Section 498 (1) lets a local government, on application by an owner, issue a development variance permit by resolution. The permit can vary provisions of the zoning bylaw and some other land use bylaws for the land it covers. Where the permit and the bylaw conflict, section 498 (3) says the permit wins.
Section 498 (2) sets the limits. A variance permit must not vary the use or density of land from what the bylaw specifies. It must not vary the application of a zoning bylaw on residential rental tenure, and it must not vary a flood plain specification. Everything else in the zoning bylaw is open to a variance request, which in practice means rules such as setbacks, height and other building dimensions.
Section 498.1 lets council delegate the power to a staff member for a minor variance to the siting, size and dimensions of buildings, off-street parking, signs or screening and landscaping. The delegating bylaw must set criteria for what counts as minor and guidelines the delegate must consider. An owner who disagrees with a delegate's decision is entitled to have council reconsider it.
Neighbours are told when council decides. Section 499 requires notice before council passes a resolution to issue a variance permit. Subsection (1.1) says that notice requirement does not apply when a delegate issues the permit under section 498.1.
The board of variance: hardship, minor, final
Section 536 requires every local government with a zoning bylaw to set up a board of variance. Its members cannot be council members, advisory planning commission members, or city staff. They serve 3-year terms without pay. Section 537 sets the size: 3 members where the municipality's population is 25,000 or less, and 5 where it is more. Vancouver's board works under section 573 of the Vancouver Charter.
Under section 540, a person may apply to the board where complying with a bylaw on the siting, size or dimensions of a building would cause them hardship. The board must notify the owners and tenants of the land and of adjacent land under section 541. Under section 542 (1), it may order a minor variance if it has heard the applicant and the people notified, finds that compliance would cause undue hardship, and is of the opinion that the variance does not do any of six listed things. These include resulting in inappropriate development of the site, harming the natural environment, varying permitted uses and densities, and defeating the intent of the bylaw. The effect on the use and enjoyment of adjacent land is also on the list.
Section 542 (2) lists orders the board must not make. It must not conflict with a covenant registered under section 219 of the Land Title Act. It must not deal with a matter covered by a land use permit, land use contract or phased development agreement, or with a flood plain specification. It must not apply to property that needs a heritage alteration authorization under Part 15, has a heritage revitalization agreement in effect, or is protected heritage property in a heritage conservation area.
Time limits apply. Under section 542 (3), if construction has not started within 2 years after the order, or within another period the order sets, the permission ends and the bylaw applies again. And section 542 (4) says the board's decision is final.
Choosing the route
Start from what needs to change. If the answer is the number of homes or the type of building, the route is rezoning, because the other two cannot vary use or density. If the answer is a setback, a height or another dimension, a development variance permit is the usual route. If the rule causes undue hardship on a minor point of siting, size or dimensions, the board of variance is a third option, with a final decision and no appeal to council.
Check the title before choosing. A covenant registered under section 219 cannot be overridden by the board of variance. If the covenant is in favour of the city, removing or changing it is a discussion with the city, separate from any variance. If it is a building scheme, Port Moody's page notes that the city is not a party to it at all.
The table below sets the three routes side by side. Before design work starts, write down which route each departure from the zone would need, because a design that depends on a rezoning carries a different schedule and risk from one that needs a single variance.
| Route | Who decides | What it can change | Limits | Sections |
|---|---|---|---|---|
| Rezoning | Council, by bylaw | Use, density, siting, size, dimensions and lot sizes | Follows the public hearing rules in section 464; inside a transit-oriented area, density within the provincial limits cannot be refused | 479, 464 |
| Development variance permit | Council by resolution, or a delegated staff member for a minor variance | Bylaw provisions such as setbacks, height and parking | Use, density, rental tenure, flood plain specifications | 498, 498.1, 499 |
| Board of variance | Independent board of 3 or 5 appointed members | A minor variance to siting, size or dimensions where compliance causes undue hardship | Use and density, section 219 covenants, listed heritage property, flood plain specifications | 536 to 542 |
Frequently asked questions
What is the difference between rezoning and a development variance permit?
Rezoning amends the zoning bylaw itself and can change the use and density allowed on a lot. A development variance permit leaves the zone in place and relaxes specific provisions for one property, such as a setback or height. Section 498 (2) bars a variance permit from changing use or density, rental tenure rules or flood plain specifications.
Can a development variance permit add units to my lot?
No. Section 498 (2) of the Local Government Act says a development variance permit must not vary the use or density of land from what the bylaw specifies. Section 481.3 treats the unit minimums as a use and density of use. Adding homes beyond what the zone allows therefore goes through rezoning.
Is a public hearing required to rezone a lot for housing in BC?
Not when the rezoning matches the official community plan and is mainly residential. Section 464 (3) says a city must not hold a hearing where an official community plan is in effect, the rezoning is consistent with it, its sole purpose is a development that is at least partly residential, and the residential part is at least half of the gross floor area. A rezoning that does not match the plan still needs one.
What is a board of variance?
It is an independent board that every local government with a zoning bylaw must set up under section 536. Its 3 or 5 members cannot be council members or staff. It can allow a minor variance to rules on the siting, size or dimensions of a building where compliance would cause undue hardship, and its decision is final.
What counts as undue hardship at a board of variance?
The Local Government Act does not define it. Section 542 (1) requires the board to find that compliance would cause the applicant undue hardship and to be satisfied that the variance is minor and passes the listed tests, such as not defeating the intent of the bylaw. Each board decides on the facts of each application.
Can the board of variance overrule a restrictive covenant?
No. Section 542 (2) of the Local Government Act says the board must not make an order that would conflict with a covenant registered under section 219 of the Land Title Act. A covenant has to be dealt with separately, with the party it was registered in favour of, before or alongside any variance request.
Can city staff approve a minor variance without council?
They can if council has delegated that power by bylaw under section 498.1. Delegation covers minor variances to the siting, size and dimensions of buildings, off-street parking, signs, and screening or landscaping. The bylaw must set criteria for what counts as minor, and an owner can ask council to reconsider a delegate's decision.
Will my neighbours be told about a variance application?
Yes, when council decides or the board of variance hears the case. Section 499 requires notice to affected owners and tenants before council passes a resolution to issue a development variance permit, though not when a delegated staff member issues it. For the board of variance, section 541 requires notice to owners and tenants of the land and of adjacent land.
How long does a board of variance approval last?
Section 542 (3) says the permission ends if construction has not started within 2 years after the order, or within a longer or shorter period the order sets. It also ends if the order sets a completion date and construction is not finished by then. After that, the original bylaw applies again.
Can I appeal a board of variance decision to council?
No. Section 542 (4) of the Local Government Act states that a decision of the board of variance is final. Council has no power under the Act to overturn it. This differs from a delegated development variance permit, where section 498.1 gives the owner a right to have council reconsider.
Does Vancouver have a board of variance?
Yes. Vancouver works under the Vancouver Charter instead of the Local Government Act, and section 573 of the Charter covers appeals to its Board of Variance. Its procedures are set by the Charter and city bylaws, so check the City's own rules before applying.
Go deeper in the Journal
- Rezoning vs building under existing zoning: which path is yours?
- Setbacks, height, and floor area: the rules that shape your multiplex
- Your zoning allows four units. Your title might not.
- The feasibility review: how to know if your lot pencils out
- From single-family lot to fourplex: the development timeline
Sources and references
Rate and regulation figures on this page were re-verified on 2026-10-23. Construction cost ranges come from Venture Pacific's own Metro Vancouver projects and are described as such wherever they appear.
- Local Government Act, Part 14, Planning and Land Use Management (sections 455, 457.1, 464, 479, 481.01, 481.3 to 481.5, 498 to 499, 525.1, 525.2, 536 to 542, 585.52)BC Laws, King's Printer. Consolidation current to 20 October 2026. Accessed 23 October 2026.
- Vancouver Charter, Part XXVII, Planning and Development (sections 565.03 and 573)BC Laws, King's Printer. Accessed 23 October 2026.
- Land Title Act, Part 14, section 219 (covenants) and section 220 (building schemes)BC Laws, King's Printer. Act current to 20 October 2026. Accessed 23 October 2026.
- Frequently Asked Questions for Bill 47 (transit-oriented areas)Province of British Columbia. Version dated 28 February 2024. Accessed 23 October 2026.
- Bulletin PLANNING-09: Small-Scale Multi-Unit HousingCity of Richmond. Bulletin dated 29 August 2024. Accessed 23 October 2026.
- City amends Zoning Bylaw to permit higher residential densities throughout BurnabyCity of Burnaby. Published 11 June 2024. Accessed 23 October 2026.
- Small-Scale, Multi-Unit Housing (SSMUH)City of Port Moody. Accessed 23 October 2026.
Let's talk about your property
A conversation, not a commitment.
Whether you're curious about the multiplex value of your land or looking to partner on a missing-middle build, we're here to start the conversation.