What a cost plus contract is, and how the builder's fee is set

A cost plus contract is a building contract where the homeowner pays the actual cost of the work, such as trade invoices, materials and site labour, plus a fee to the builder. The Canadian Construction Documents Committee's standard cost plus form, CCDC 3 2016, describes that fee as a percentage or a fixed amount applied to actual costs. Most of the owner's protection sits in four parts of the contract: how the fee is set, what counts as cost, whether the total has a cap such as a guaranteed maximum price, and which records the owner can see. In British Columbia, section 41 of the Builders Lien Act also lets an owner ask the contractor in writing for the terms of any subcontract, with an answer due within 10 days.

Part of Construction contracts in BC: how a build is priced, paid for and changed. Figures re-verified 2026-10-24.

Key takeaways

  • CCDC 3 2016, the national standard cost plus form, pays the contractor actual cost plus a percentage or fixed fee applied to actual costs.
  • A percentage fee rises with every dollar of cost. A fixed fee stays the same unless the scope changes, so the contract must say which scope changes adjust it.
  • A guaranteed maximum price puts a cap on the total. CCDC 5B 2025 offers it as an option, along with a shared savings version and conversion to a stipulated price.
  • The definition of cost of the work needs as much attention as the fee: the builder's own labour rates, supervision, equipment, rework and discounts each need a written rule.
  • Under section 41 of the Builders Lien Act, an owner may ask the contractor in writing, at any time, for the terms and price of any subcontract, and the contractor must answer within 10 days.
  • Money a contractor receives on account of the price is a trust fund for the trades (section 10), and the 10% holdback in section 4 applies to cost plus payments.

What the homeowner pays under cost plus

A cost plus contract has two parts to its price. The first is the cost of the work: what the builder actually pays trades, suppliers and site workers to build the project. The second is the builder's fee, which pays for the builder's management, overhead and profit. The Canadian Construction Documents Committee (CCDC), the national committee that writes Canada's standard construction contracts, publishes a cost plus form called CCDC 3 2016. Its own description is a standard prime contract between owner and prime contractor to do the work "on an actual-cost basis, plus a percentage or fixed fee which is applied to actual costs."

If you are still deciding which contract type to use, read fixed price or cost plus first. In short, a fixed price contract puts the gap between estimate and real cost on the builder, who prices that risk into one number. A cost plus contract puts the gap on the homeowner and shows the real costs in return. This chapter starts after that choice, with the terms that decide whether a cost plus contract works for the person paying.

On a Vancouver renovation or a new duplex in Burnaby, the same four questions come up. How is the fee set? What counts as cost? Is there a cap on the total? And what records does the homeowner get to see? A contract that answers all four in writing lets both sides settle a disagreement by reading a clause. A contract that leaves them open sends the question to a negotiation in the middle of the build, when the homeowner has fewer choices.

Percentage fee or fixed fee

A percentage fee is a set percentage added to every dollar of cost. If the cost of the work goes up, the fee goes up with it in the same proportion. The method is simple to apply and suits a project whose scope is unclear at signing, because the fee follows the work wherever it goes. The weakness is the incentive: the builder earns more when the project costs more. The contract then has no built-in reason to hold cost down, so regular cost reporting has to do that job.

A fixed fee is one amount, agreed at signing, for the builder's management and profit on a defined scope. The fee stays the same when the cost of that scope rises or falls. This removes the incentive problem and moves the argument to a new place: what counts as a change in scope. If the homeowner adds a room, the fee should rise. If a trade price goes up, it should stay where it is. The contract needs a clause that says which events adjust the fee and by how much, for example a stated percentage applied to the cost of approved changes only.

Some contracts mix the two, with a fixed fee for the base scope and a percentage fee on change orders. Others step the percentage down as cost passes set levels. Any of these can work. What matters is that the method is written down, the fee shows as its own line on every payment request, and the homeowner can check the arithmetic against the invoices behind it.

A cap on the total: guaranteed maximum price

A guaranteed maximum price, often shortened to GMP, is a cap on what the owner pays for a defined scope under a cost plus contract. Costs up to the cap are paid as cost plus fee. In the usual meaning of the term, costs above the cap are the builder's to carry, except where the owner changes the scope; the contract's own definition is what applies. The CCDC construction management form for services and construction, CCDC 5B 2025, lists a GMP option. Its description also names a "GMP Plus Percentage Cost Savings" option, where savings under the cap are shared, and the choice to convert the contract into a stipulated price contract, which is a fixed price.

A cap needs the same thing a fixed price needs: drawings complete enough to price. A builder asked for a GMP on a house that has not been opened up will set the cap high, to cover what might be behind the walls. On new construction with a full drawing set, a GMP can give a homeowner much of the certainty of a fixed price while the invoices stay visible.

Read three things in any GMP clause. First, the exact scope the cap covers, listed by drawing and specification number. Second, the list of events that raise the cap, such as owner changes, concealed conditions or permit requirements added after signing. Third, how shared savings are split and when they are paid. A cap that rises for every unexpected condition gives the homeowner little protection.

What counts as cost of the work

The fee gets the attention, but the definition of cost of the work sets how much of the money is billable. Read that definition in the contract line by line. Each item in the table below is a place where two people can read the same words in different ways. Write the answer into the contract before signing.

Two items need the closest reading. The first is the builder's own crew. If the builder's carpenters are billed at an hourly rate, that rate already includes some profit, and the fee is then added on top. Agree the rates in a schedule attached to the contract. The second is rework. When a trade has to redo faulty work, the contract should say whether the owner pays for the redo as cost, or whether the trade or the builder carries it.

ItemThe question to settle in writing
Trade and supplier invoicesAre they billed at the invoice amount, with copies attached to each payment request?
Builder's own site labourWhat hourly rate applies to each role, and is it fixed for the whole project?
Site supervision and project managementIs the supervisor's time billed as cost, or paid out of the fee?
Builder-owned tools and equipmentIs there a rental rate, and is it capped at the price of buying the item?
Permits, insurance and site servicesWhich does the owner pay directly, and which flow through the builder?
Rework of faulty workWho pays to redo work that failed inspection or was built wrong?
Discounts, rebates and returnsAre trade discounts and returned materials credited back to the owner?
Head office costsAre office rent, accounting and estimating paid out of the fee only?
Questions the cost of the work definition should answer

Open books: the records an owner can see

Open book means the owner sees the builder's real costs: every invoice, timesheet and credit that makes up the cost of the work. In a cost plus contract this is the basis of trust, so write it down. A useful clause lists the documents attached to each payment request, gives the owner the right to inspect the builder's project records on notice, and requires those records to be kept for a set time after completion.

British Columbia law adds a right that exists whatever the contract says. Under section 41 (2) of the Builders Lien Act, an owner may ask the contractor in writing, at any time, for the terms of any subcontract, including the parties, the subcontract price and the state of accounts between them. Section 41 (3) gives the contractor 10 days to comply. If the contractor does not answer, section 41 (5) lets the owner withhold further payments until it does. A person who misstates the information, knowingly or through negligence, is liable for the resulting loss under section 41 (4). Section 42 (2) makes void any agreement that the Act will not apply, so a contract cannot remove these rights.

Two more sections matter on a cost plus job. Section 10 says money a contractor receives on account of the contract price is a trust fund for the people engaged on the project, and the contractor must not divert it until they are paid. And section 4 requires the owner to hold back 10% of the greater of the value of the work provided and the payments made on account of the price. Each cost plus progress payment is a payment on account of the price, so the holdback applies to it. The payments and holdbacks chapter covers how it is kept and released.

One last point. A cost plus contract with no budget has nothing to measure against. Ask for a written estimate at signing, broken down by trade, and a monthly report that shows cost to date, cost still to come, and the forecast total against that estimate. The estimate gives both sides a number to compare each month's costs with.

Frequently asked questions

What is a cost plus contract in plain words?

It is a building contract where you pay what the work actually costs, plus a fee to the builder. The cost covers trade invoices, materials and site labour. The fee is either a percentage of that cost or a fixed amount. The national standard form for this type is CCDC 3 2016.

Is a percentage fee or a fixed fee better for a homeowner?

A fixed fee suits a homeowner when the scope is well defined, because the builder's pay stays the same as cost grows. A percentage fee suits a project whose scope will change many times, because the fee follows the work without a new negotiation for each change. With either method, write down which events change the fee.

What is a guaranteed maximum price in a construction contract?

A guaranteed maximum price, or GMP, is a cap on what the owner pays for a defined scope under a cost plus contract. The builder carries costs above the cap, except for owner changes and other events the contract lists. CCDC 5B 2025 offers a GMP option and a version where savings under the cap are shared.

What events can raise a guaranteed maximum price?

Only the events the contract lists. These normally include owner changes to the scope, and may include concealed conditions or new permit requirements. Read the list before signing, because a long list leaves the cap with little force.

Can a builder bill its own crew at a marked-up hourly rate under cost plus?

Only if the contract allows it. If the builder's own carpenters are billed at an hourly rate that already includes profit, and the fee is added on top, the owner pays profit twice on that labour. Agree a rate schedule for each role in the contract.

Can I see what my builder pays each subcontractor?

Yes. Section 41 of BC's Builders Lien Act lets an owner ask the contractor in writing, at any time, for the terms and price of any subcontract and the account balance. The contractor has 10 days to comply. If it does not, the owner may withhold further payments until it does.

Who keeps supplier discounts and rebates on a cost plus job?

The party the contract names. Under cost plus the owner pays actual cost, so discounts, rebates and credits for returned materials logically belong to the owner. Only a written clause in the definition of cost of the work makes that binding.

Does a cost plus contract still need an estimate?

Yes. A cost plus contract has no fixed sum, so a written estimate broken down by trade is the only measure of whether the job is on budget. Ask for a monthly report that compares cost to date and forecast cost against it.

Is CCDC 3 the standard cost plus contract in Canada?

CCDC 3 2016 is the cost plus form published by the Canadian Construction Documents Committee, the national committee that writes standard construction contracts. It is a prime contract between owner and contractor, priced at actual cost plus a percentage or fixed fee. The CCDC sells it in electronic format only.

Does the 10% builders lien holdback apply to cost plus payments?

Yes. Section 4 of the Builders Lien Act requires a holdback of 10% of the greater of the value of work provided and the payments made on account of the price. A cost plus progress payment is a payment on account of the price, so the holdback applies to it.

Is the money I pay a cost plus builder protected for the trades?

Section 10 of the Builders Lien Act makes money a contractor receives on account of the contract price a trust fund for the people engaged on the project. The contractor must not divert it until they are paid. The rule protects the trades who could otherwise file a lien against the property.

Go deeper in the Journal

Sources and references

Rate and regulation figures on this page were re-verified on 2026-10-24. Construction cost ranges come from Venture Pacific's own Metro Vancouver projects and are described as such wherever they appear.

  1. CCDC 3 2016, Cost Plus ContractCanadian Construction Documents Committee. Accessed 24 October 2026.
  2. CCDC 5B 2025, Construction Management Contract for Services and ConstructionCanadian Construction Documents Committee. Accessed 24 October 2026.
  3. About the Canadian Construction Documents CommitteeCanadian Construction Documents Committee. Accessed 24 October 2026.
  4. Builders Lien Act, S.B.C. 1997, c. 45 (sections 1, 2, 4, 5, 7, 8, 10, 15, 17, 19, 20, 23, 24, 26, 33, 34, 41, 42 and 45)BC Laws, King's Printer. Act current to 20 October 2026. Accessed 24 October 2026.