What has to be in place before you can apply

In British Columbia a new home cannot receive a building permit until the province's builder licensing and warranty requirements are already satisfied. The city asks for a New Home Registration Form, which is the proof that a licensed residential builder is in place with home warranty insurance arranged, or that the owner holds an approved Owner Builder Authorization. Owners who discover this at the permit counter lose weeks, because both routes take time to arrange and neither can be backdated.

Part of Building permits in Metro Vancouver. Figures re-verified 2026-09-23.

Key takeaways

  • A New Home Registration Form is needed before a building permit for a new home is issued.
  • A residential builder must be licensed with BC Housing before construction starts.
  • An Owner Builder Authorization is required before construction anywhere in BC, even where no building permit is needed.
  • An owner builder must manage the construction personally, and hiring a third party to do it carries penalties of up to $25,000.
  • An owner builder is personally liable for construction defects for 10 years.
  • Envelope repair work crosses into licensing and warranty territory at 60 percent of a cladding surface and $10,000.

The document the city asks for first

Before a building permit for a new home is issued, BC Housing requires a New Home Registration Form as proof of licensing and home warranty insurance. The requirement applies across the province, and BC Housing states that even in areas where building permits are not required, the owner must still have an approved Owner Builder Authorization before starting to build.

This is the step that most often catches homeowners who have planned their schedule around design and permit review alone. The registration is a separate process with a separate organisation, and the city will not move the permit forward without it.

There are two ways to satisfy the requirement. Either a licensed residential builder takes the project on and arranges third party home warranty insurance, or the owner obtains an Owner Builder Authorization and builds the home themselves. The two routes carry different obligations and different risk.

Building with a licensed residential builder

BC Housing requires a residential builder to hold a licence before starting construction on a new project, and to keep that licence current until every home enrolled in home warranty insurance has been completed, or sold in the case of a developer.

For the homeowner, this route means the warranty is carried by a third party insurer rather than by the owner personally. The coverage follows the standard tiers: two years on materials and labour, five years on the building envelope, and ten years on structural defects.

It also means the licensing requirement is the builder's to satisfy, which is one of the practical arguments for engaging the builder before the permit application rather than after it. A builder brought in early can arrange the registration in parallel with design instead of after the drawings are finished.

Building as an owner builder

An owner builder is an individual authorised by BC Housing to build one new home for personal use, without holding a builder licence and without third party home warranty insurance. The authorisation must be obtained before construction starts, in every area of British Columbia, whether or not building permits are required there.

The eligibility rules are specific. BC Housing's regulatory bulletin for owner builders, revised September 2018, sets out that the applicant must be an individual holding a registered interest in the land, which means fee simple, a life interest, or a long term lease of at least 15 years. The applicant must intend to use the home personally for at least one year after first occupancy, and must not sell or transfer their interest in the land during construction or for at least one year after the home is built. A person who has already held an authorisation must wait at least 18 months from first occupancy of the previous owner built home, and that waiting period increases for repeat owner builders. The applicant must also pass the Owner Builder Authorization examination with a mark of 70 percent or better.

The obligation that matters most sits after the build. An owner builder must build or directly manage the construction personally. Engaging a builder, construction manager, or project manager to perform that role is an offence under the Homeowner Protection Act for both parties, carrying penalties of up to $25,000 and possible prosecution. The owner builder then remains responsible for the overall construction of the home for 10 years, and is personally liable to any subsequent purchaser during that period unless voluntary warranty insurance was arranged. The statutory protection mirrors the insured tiers: two years on materials and labour, five years on the building envelope, and ten years on structural defects.

Renovations that cross into licensing territory

Most renovations sit outside builder licensing. Building envelope repair is the exception, and the threshold is precise. BC Housing defines a building envelope renovation as work to repair defects that allow unintended water penetration, or to repair the damage that penetration caused. Licensing and warranty requirements apply when the work affects 60 percent or more of any cladding surface and costs $10,000 or more, which becomes $2,000 per unit in a multi unit building. Both conditions have to be met.

Where the work qualifies, the permit application needs a Building Envelope Renovation Schedule, signed by the consultant, the licensed renovator, and the owner or strata corporation, with the warranty provider's approval.

This is the rule that turns a large re-cladding job into a licensed project. An owner planning to replace siding on most of a house should establish which side of the threshold the work falls on before pricing it, because the answer changes who can lawfully perform it.

Frequently asked questions

What is a New Home Registration Form and why does the city want it?

A New Home Registration Form is BC Housing's proof that a new home has a licensed residential builder in place with home warranty insurance arranged. Municipalities in British Columbia require it before issuing a building permit for a new home. It exists so that warranty coverage is confirmed before construction starts rather than afterwards. Owners building under an Owner Builder Authorization satisfy the requirement through that authorisation instead.

Can I build my own house in British Columbia without a licensed builder?

Yes, through an Owner Builder Authorization from BC Housing, which must be approved before construction starts anywhere in British Columbia. The owner must build or directly manage the construction personally. Hiring a builder or construction manager to perform that role is an offence under the Homeowner Protection Act for both parties, with penalties reaching $25,000. The owner then carries responsibility for defects for 10 years.

How long must an owner builder live in the home?

BC Housing's owner builder bulletin, revised September 2018, requires the applicant to intend to use the home personally for at least one year after first occupancy, and to avoid selling or transferring their interest in the land during construction or for at least one year after the home is built. Selling earlier conflicts with the terms the authorisation was granted under.

How often can someone be an owner builder?

Under BC Housing's eligibility rules, an applicant must not have been issued a previous Owner Builder Authorization within at least 18 months of first occupancy of their last owner built home, and that waiting period increases for repeat owner builders. The rule also extends to household members, since an applicant must not ordinarily live with someone who holds an authorisation inside the same window.

Is there an exam to become an owner builder?

Yes. BC Housing requires applicants to pass the Owner Builder Authorization examination with an overall mark of 70 percent or better. The exam covers construction basics along with the statutory obligations and requirements that come with building your own home. It follows the pre screening and application stages, and BC Housing sends exam details once it confirms the applicant meets the eligibility criteria.

What happens if an owner builder sells the house within 10 years?

The owner builder must give any prospective purchaser a disclosure notice obtained from BC Housing's Licensing Department, stating that the home was owner built and whether home warranty insurance is in place. Unless voluntary insurance was arranged, the owner builder remains personally liable for construction defects for 10 years to every subsequent purchaser in that period, and that liability cannot be waived by contract.

When does a re-cladding job need a licensed renovator?

BC Housing's building envelope renovation rules apply when the work affects 60 percent or more of any cladding surface and costs $10,000 or more, which is $2,000 per unit in a multi unit building. Both conditions must be met. Work at that scale requires a licensed renovator, warranty coverage, and a signed Building Envelope Renovation Schedule submitted with the permit application.

What is a Building Envelope Renovation Schedule?

It is the BC Housing form required to obtain a building permit for a qualifying building envelope renovation. It carries signatures from the consultant, the licensed renovator, and the owner or strata corporation, along with the warranty provider's approval. The completed schedule and its supporting documents go to the municipality or regional district as part of the permit application for envelope repair work above the licensing threshold.

Does a builder need to be licensed before the permit application or before construction?

BC Housing requires a residential builder to be licensed before starting construction on a new project, and the New Home Registration Form that proves licensing and warranty is needed before the building permit is issued. In practice this means the builder must be appointed early enough to complete registration while the permit application is in review, rather than once the permit is ready.

Do these rules apply in areas with no building permit requirement?

Yes. BC Housing states that in areas of British Columbia where building permits are not required, a person must still be a licensed residential builder with home warranty insurance arranged, or hold an approved Owner Builder Authorization, before construction starts. The licensing and warranty system runs on provincial law rather than on municipal permitting, so the absence of a local permit changes nothing.

Go deeper in the Journal

Sources and references

Rate and regulation figures on this page were re-verified on 2026-09-23. Construction cost ranges come from Venture Pacific's own Metro Vancouver projects and are described as such wherever they appear.

  1. Regulatory Bulletin No. 4, Information for Owner BuildersBC Housing, Licensing and Consumer Services. Bulletin revised September 2018. Accessed 23 September 2026.
  2. Apply to Become a Licensed Residential Builder in B.C.BC Housing. Accessed 23 September 2026.
  3. Building Envelope Renovations, licensing and warranty requirementsBC Housing. Accessed 23 September 2026.