Change orders, allowances and delays: how a contract handles the parts that move

A renovation price is fixed only for the work written into the contract. Four things can move it after signing: changes the owner asks for, allowances for items not yet chosen, conditions found once the building is opened, and delay. A well-written contract handles each in writing before it happens: how a change is priced and approved, how each allowance is settled against the real cost, who controls any contingency, and which delays give the builder more time or more money. In British Columbia, the Builders Lien Act's 10% holdback applies to the value of changed work in the same way as to the original scope.

Part of Construction contracts in BC: how a build is priced, paid for and changed. Figures re-verified 2026-10-24.

Key takeaways

  • A fixed price covers the scope in the contract documents. Owner changes, allowance overruns and excluded conditions are added through change orders.
  • A change order should state the work, the price and how it was worked out, the effect on the schedule, and be signed before the work starts.
  • The markup on changes and the rates for change work should be agreed in the contract before any change is needed.
  • Each allowance should state what it covers (supply only, or supply and install), the amount, the selection deadline and how differences are settled.
  • A contingency should be named as the owner's or the builder's, with a rule for who approves spending it and what happens to the balance.
  • Under section 1 (5) of the Builders Lien Act, 30 days with no work deems a contract abandoned, unless the stop had a listed cause.

Is a renovation a fixed cost?

Only in part. Under a fixed price contract, the builder carries the cost of the work described in the contract documents. Everything else moves the price: changes the owner asks for, allowances replaced by real selections, and conditions the contract excludes, such as rot or hazardous materials found behind finishes. Under a cost plus contract, only the fee method is fixed, and the price is the actual cost of whatever is built.

The reasons renovation estimates move are covered in scope and unknowns. This chapter covers the paperwork: how a contract for a Vancouver character house, a Burnaby basement suite or a Surrey addition should record each change to the price, so the final price can be traced from the contract sum through every approved change.

A final account is the document that does that tracing. It starts with the contract sum, adds and subtracts every signed change order and allowance adjustment, and ends at the amount owing. Ask that the contract require one before the final payment.

What a change order should contain

A change order is a written amendment to the contract that changes the scope, the price, the time, or more than one of them. The CCDC publishes a separate guide on how its standard contracts treat changes, CCDC 16 2024, which covers the main terms, how changes proceed, the ways the contract price can be adjusted, and claims. CCDC 2, the standard fixed price form, includes changes among the subjects its conditions cover.

Whatever form the contract uses, a change order should show a number and date, a description of the change with any revised drawing, the price and how it was worked out, the effect on the completion date, and the signatures of the person authorised by each side. The contract should name who can sign for the owner. On a multiplex with several owners or partners, name one person, or require two signatures, so the builder knows whose approval counts.

One rule protects both sides: no extra work is paid without a signed change order, and no change work starts before it is signed. Some work cannot wait for a price. A contract can allow the owner to give a written instruction to proceed, with the price settled afterwards by a method agreed in advance, such as cost plus the change fee. That lets work continue without leaving the price open.

How changes are priced

Changes are priced in one of three ways. A lump sum is one quoted price for the change, agreed before the work. Unit rates use prices agreed in the contract for measured quantities, such as per square metre of drywall. Cost plus prices the change at actual cost plus an agreed fee, which suits work that cannot be measured until it is done.

The markup on a change needs its own clause. Settle in the contract, before any change is needed, the percentage the builder adds for overhead and profit on change work, whether the same percentage is credited back when work is deleted, and the hourly rates for the builder's own crew. If deleted work is credited at cost while added work carries full markup, every swap of one item for another costs the owner money.

Ask for change pricing broken down into labour, material, trade costs and markup. The breakdown lets the owner compare the change with the original contract pricing, and it is the record a mediator or arbitrator will read if the price is disputed.

Allowances and provisional amounts in the contract

An allowance is an amount in the contract for an item the owner has not yet chosen, such as tile, plumbing fixtures or appliances. A provisional amount, sometimes called a provisional sum, covers work whose extent is unknown at signing, such as rock removal or a length of drain replacement. Both are estimates inside a fixed price. When the real cost is known, the difference is added or credited.

For each allowance, the contract should state five things. What the amount covers: supply only, or supply and installation. Whether the builder's markup sits inside the amount or is added to any overrun. The date by which the owner must choose, because a late choice can delay the work. How the difference is calculated, by invoice. And whether savings are credited in full.

Set allowances from real selections where you can. A low allowance makes a quote look cheaper at signing and moves the money into change orders later. If two builders' prices differ, compare their allowances line by line before comparing totals.

Contingency: whose money, and who approves it

A contingency is money set aside for costs nobody can price at signing. In a contract it can sit in two places. An owner's contingency is held by the owner, outside the contract sum, and spent only through signed change orders. A builder's contingency is inside the contract price, and under a fixed price contract the builder keeps any part it does not spend unless the contract says otherwise.

Whichever you use, write down who approves spending, what reports the owner gets, and what happens to the balance at the end. On cost plus work, a contingency line in the estimate is a forecast, and the owner pays actual cost whether or not the line is used. The contract should say how the builder reports against it each month.

Delays, extensions and the completion date

A contract with no completion date gives the owner nothing to measure delay against. Write in a start date and either a completion date or a number of working days, then list the events that extend it. Common ones are owner changes, late owner selections, permit or inspection waits outside the builder's control, extreme weather and concealed conditions. Each extension should be asked for in writing within a set number of days of the event.

Liquidated damages are an amount per day, agreed in advance, that the builder pays if it finishes late without an allowed reason. They save both sides from proving the actual loss later. The amount should relate to the owner's real cost of delay, such as rent for another place to live, and the clause should say whether it is the owner's only remedy for delay.

Delay also has a statutory effect. Under section 1 (5) of the Builders Lien Act, a contract is deemed abandoned if no work is done for 30 days, unless the stop had a listed cause such as a strike, weather or a court order. Abandonment starts the 45-day lien filing period and the 55-day holdback period. If no one has worked on your site for a month, write to the builder, ask why, and keep a dated record, because the answer affects the lien dates. The disputes and ending chapter covers what to do if the builder does not come back.

ItemWho decidesWhat the contract should state
Owner changeOwner, by signed change orderPricing method, markup, schedule effect, who may sign
AllowanceOwner, by selectionAmount, what it covers, selection deadline, how overruns and savings are settled
Provisional amountMeasured on siteUnit rates or cost plus method, and how quantities are recorded
Concealed conditionFound on site, priced by change orderWhich conditions are excluded from the fixed price, and how they are priced
ContingencyAs named in the contractWho holds it, who approves spending, what happens to the balance
DelayDepends on the causeEvents that extend time, notice periods, liquidated damages if any
How a contract should record each part that moves

Frequently asked questions

Is a renovation a fixed cost once the contract is signed?

Only for the work written into the contract, and only under a fixed price contract. Owner changes, allowances replaced by real selections, and conditions the contract excludes are added through change orders. Under cost plus, the price is the actual cost of whatever is built, plus the fee.

What should a written change order include?

A number and date, a description of the change with any revised drawing, the price and how it was worked out, the effect on the completion date, and signatures from the authorised person on each side. Sign it before the change work starts.

Can a builder start extra work before I sign a change order?

Only if the contract allows it. A contract can let the owner give a written instruction to proceed, with the price settled afterwards by a method agreed in advance. Without that clause, the safe rule is no signed change order, no extra work and no extra payment.

How is the price of a change order worked out?

By the method the contract sets: a lump sum quoted before the work, unit rates agreed in the contract, or actual cost plus an agreed fee. Ask for each change priced as labour, material, trade costs and markup, so it can be compared with the original pricing.

Should a credit for deleted work include the builder's markup?

The contract should say. If added work carries full markup and deleted work is credited at cost only, every swap of one item for another costs the owner money. Agree the treatment of credits in the same clause that sets the markup on changes.

What is a provisional amount in a building contract?

It is a sum inside the contract price for work whose extent is unknown at signing, such as rock removal or a length of drain replacement. Once the work is measured or done, the real cost replaces the provisional amount, and the difference is added or credited.

What happens when an allowance item costs less than the allowance?

The owner should receive a credit for the difference, but only the contract makes that binding. Check that the allowance clause credits savings in full and says whether any markup in the allowance is credited too.

Who controls the contingency in a construction contract?

The party the contract names. An owner's contingency sits outside the contract sum and is spent only by signed change order. A builder's contingency sits inside the price. Write down who approves spending and what happens to the unused balance.

What are liquidated damages in a construction contract?

They are an amount per day, agreed in advance, that the builder pays if it finishes late without an allowed reason. The amount should relate to the owner's real cost of delay, such as rent, and the clause should say whether it is the only remedy for delay.

Does a 30-day stop in work mean my builder has abandoned the job?

For the Builders Lien Act, yes, unless the stop had a listed cause such as a strike, weather or a court order. Section 1 (5) deems the contract abandoned, which starts the 45-day lien filing period and the 55-day holdback period. Whether you can end the contract depends on its termination clause.

What is a final account at the end of a build?

It is a statement that starts with the contract sum, adds and subtracts every signed change order and allowance adjustment, and ends at the amount owing. Ask the contract to require one before the final payment.

Can a late selection by the owner delay the completion date?

Yes, if the contract lists late owner selections as an event that extends time. Each allowance should carry a selection date, so both sides know when a late choice starts to move the schedule.

Go deeper in the Journal

Sources and references

Rate and regulation figures on this page were re-verified on 2026-10-24. Construction cost ranges come from Venture Pacific's own Metro Vancouver projects and are described as such wherever they appear.

  1. CCDC 16 2024, Guide to Changes in the ContractCanadian Construction Documents Committee. Accessed 24 October 2026.
  2. CCDC 2 2020, Stipulated Price ContractCanadian Construction Documents Committee. Accessed 24 October 2026.
  3. Builders Lien Act, S.B.C. 1997, c. 45 (sections 1, 2, 4, 5, 7, 8, 10, 15, 17, 19, 20, 23, 24, 26, 33, 34, 41, 42 and 45)BC Laws, King's Printer. Act current to 20 October 2026. Accessed 24 October 2026.